REFERENCES – PROJECT MANAGEMENT
AUDI FAW NEV Greenfield Production Facility Project, Changchun, PCM
Type: PCM, Cost budget, Due diligence, Permitting/ Design and Construction management full scope for entire site
Duration: 40 months, 2021 - 2025
Construction area: 600,000 m²
AUDI FAW NEV Body Shop
Type: PCM, Cost budget, Due diligence, Permitting/ Design and Construction management full scope for entire site
Duration: 30 months, 2021 – 2024
Construction area: 134,000 m²
AUDI FAW NEV Paint Shop
Type: PCM, Cost budget, Due diligence, Permitting/ Design and Construction management full scope for entire site
Duration: 30 months, 2021 – 2024
Construction area: 56,000 m²
AUDI FAW NEV Technical Center
Type: PCM, Cost budget, Due diligence, Permitting/ Design and Construction management full scope for entire site
Duration: 30 months, 2021 – 2024
Construction area: 64,000 m²
Würth Haiyan Phase II Central Distribution Center
Type: EPCM: Specifications & Design Management; Construction Management
Start: 8/2016
Duration: 20 months
Construction area: 47,000 m²
Würth Haiyan Phase II Central Distribution Center
Type: EPCM: Specifications & Design Management; Construction Management
Start: 8/2016
Duration: 20 months
Construction area: 47,000 m²
Boysen Exhaust Systems Langfang New Production Facility Project
Type: Concept Design, Detailed design/ Permitting
Start: 02/2013
Duration: 15 months
Construction area: 21,000 m²
DPTS (Daimler Spare Parts) Renovation, Dezhou, PCM
Type: Concept Design/ Detailed Design/ Permitting/ Construction Management
Start: 03/2023
Duration: 10 months
Area: 12,117 sqm